Road Works Completed in Kenya

Public Date:2021-02-22

Recently, the 17.3 km asphalt double surface dressing of the second branch road under contract RWC-444 in Kenya was completed and opened to traffic, and the whole contract was completed on time. 

The works is located in the west of Kenya, with a total length of 29.3km, comprising part of the 10,000 km road programme. Construction was started on August 14, 2018, and completed on February 14, 2021. 

During the work period, the project team formulated the COVID-19 prevention and control plan according to company requirements, and resumed work in time and in order. After the resumption of work, they completed five milestone tasks in seven months with improved efficiency, as a result of which the whole contract was completed on time, even though site work had been suspended for half a year.