Recently, the Balihe pump station works of the Yinghe River comprehensive treatment phase I project undertaken by the company won the "Yuwang Cup" of year 2020, the highest honor for a water conservancy project in Anhui province, China.

The pump station is equipped with six vertical axial flow pumps with a total installed capacity of 5,100kw. The design flow of pumping is 60 cu.m/s, and the design flow of diversion is 16.5 cu.m/s. The scope of works includes inlet gates, forebay, station body and maintenance room, management room, workshop and substation, etc.

The works has significantly improved the flood control capacity of the project area. During the flood season in 2020, the accumulated drainage volume reached 100 million cu.m, eliminating the risk of waterlogging and ensuring the safety of people's lives and property.